HYDERABAD: Hyderabad-based construction firm KNR Constructions has completed the Bijapur-Hungund toll road of National Highways Authority of India (NHAI) nearly 11 months ahead of schedule and claimed it a record in the history of Indian highways.
KNR Constructions Ltd has announced it has completed the work of a 97 km road project located on NH13 on the Bijapur-Hungund section. The project was completed in 582 days against schedule duration of 910 days (328 days ahead of schedule).
With refer to the receipt of an EPC order worth Rs. 825 Crores towards “4 Laning of Bijapur — Hungund Section of NH-13 from Km 102.00 to Km 202.00 in the State of Karnataka under NHDP Phase III" in the State of Karnataka from Bijapur Hungund Tollway ...
The Bijapur-Hungund Tollway Pvt. Ltd. (BHTPL) subsidiary of Sadbhav Engineering Ltd and a SPV incorporated in respect of the following project has achieved Commercial Operational Date (COD) for entire (100%) project length on April 09, 2012 against the ...